Friday, July 30, 2010

Tutorial 4 - schedule



This tutorial is create a schedule and perform a network analysis (AON) based on our WBS.

Our project estimated completion time is 909days [(365 days x 3) - (52days x 3) - 30holiday]
project start on 24 May 2010
earliset finish time = 904 days (14/5/2013)
Float time = 5 days